Glyndebourne Restaurant Refurb

Project Title: Glyndebourne Wallop Restaurant Refurbishment

Main Contractor: Bramber Construction

Elect Consultant: CMS Building Services Ltd

Project Value: £254,000.00

Package: Electrical & Mechanical

Description: Refurbishment of existing Wallop Restaurant

Programme: 29 weeks

Description of works:

A complete new electrical system was installed incorporating a new sub-mains distribution system, distribution boards and flush small power and lighting systems. A complete heating and ventilation system was installed incorporating air handling plant and fan coil units and also boilers were installed. Electrical, heating and ventilation accessories were incorporated into the interior design to produce n aesthetically sympathetic finish in line with the clients wishes

Specialist Sub-Contractor Packages Included:

Data & Voice

Fire Alarm

Security